The scheme consisted of
the construction of two office blocks in Newton Abbot totalling 2500m2. Both buildings
were three storeys high, steel framed and included
concrete plank floors. Brick faced cavity walls were
broken up with cladding panels and were supported on
RC ground beams and piled foundations. Extensive re-routing
of sewers had to be undertaken before works could commence. |